Caltrans Logo

Gerald Desmond Bridge Replacement Project

Description: In Long Beach, at the Port of Long Beach, at the Gerald Desmond Bridge. Replace bridge.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Long Beach
Zip Code 90012, 90806
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
 
County/State Route Los Angeles 710
Postmile Begin/End 3.7 6
Project Benefits
 Benefit Baseline Actual
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Long Beach Allison Yoh 562-283-7188   allison.yoh@polb.com
Design (PS&E) Phase
Port of Long Beach Allison Yoh 562-283-7188   allison.yoh@polb.com
Right of Way Phase
Port of Long Beach Allison Yoh 562-283-7188   allison.yoh@polb.com
Construction Phase
Port of Long Beach Allison Yoh 562-283-7188   allison.yoh@polb.com
 
Corridor System Management Plan
Port of Long Beach Allison Yoh 562-283-7188   allison.yoh@polb.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$153,657 $0 $153,657
SHOPP Augmentation
$0 $0 $0
Ports Inf, Sec, & AQ
$0 $0 $0
Non-bond Funding
State/Federal*
$346,343 $47,960 $394,303
Local**
$460,203 $327,898 $788,101
 
Total**** $960,203 $375,858 $1,336,061

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$11,862 $0 $11,862 $5,746
Design(PS&E)
$37,878 $361 $38,239 $44,380
Right of Way
$128,104 $196,596 $324,700 $109,790
Construction
$782,359 $178,901 $961,260 $798,693
 
Total* $960,203 $375,858 $1,336,061 $958,608

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100  03/29/2003 

08/09/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100  08/16/2012 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
94  08/16/2012 

02/26/2021 


Begin Construction Phase

End Construction Phase
 

 
 

 
 

 
94  06/07/2013 

04/30/2021 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
94  12/27/2019 

02/15/2023 


Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.