Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Gerald Desmond Bridge Replacement Project |
Description: In Long Beach, at the Port of Long Beach, at the Gerald Desmond Bridge. Replace bridge.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Long Beach |
Zip Code | 90012, 90806 |
Senate District |
27 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
County/State Route | Los Angeles 710 |
Postmile Begin/End | 3.7 6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Long Beach | Allison Yoh | 562-283-7188 | allison.yoh@polb.com | |
Design (PS&E) Phase |
Port of Long Beach | Allison Yoh | 562-283-7188 | allison.yoh@polb.com | |
Right of Way Phase |
Port of Long Beach | Allison Yoh | 562-283-7188 | allison.yoh@polb.com | |
Construction Phase |
Port of Long Beach | Allison Yoh | 562-283-7188 | allison.yoh@polb.com | |
Corridor System Management Plan |
Port of Long Beach | Allison Yoh | 562-283-7188 | allison.yoh@polb.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$153,657 | $0 | $153,657 | ||||
SHOPP Augmentation |
$0 | $0 | $0 | ||||
Ports Inf, Sec, & AQ |
$0 | $0 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$346,343 | $47,960 | $394,303 | ||||
Local** |
$460,203 | $327,898 | $788,101 | ||||
Total**** | $960,203 | $375,858 | $1,336,061 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$11,862 | $0 | $11,862 | $5,746 | |||
Design(PS&E) |
$37,878 | $361 | $38,239 | $44,380 | |||
Right of Way |
$128,104 | $196,596 | $324,700 | $109,790 | |||
Construction |
$782,359 | $178,901 | $961,260 | $798,693 | |||
Total* | $960,203 | $375,858 | $1,336,061 | $958,608 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | 03/29/2003 08/09/2010 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | 08/16/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
94 | 08/16/2012 02/26/2021 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
|
|
|
94 | 06/07/2013 04/30/2021 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
|
|
|
94 | 12/27/2019 02/15/2023 |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.